Aluminium die cast machines

The scope of work was to offload from a critical area of production and manoeuvre through into the main die cast machine area. Allelys then had to offload for a second time and install the units into their final position.

Two of the installations included a fixed plate weighing 57te and a moving plate weighing 87te. The components were delivered to site from Europe on a multi axle transport which needed to be offloaded inside. Due to the space restrictions within the building, Allelys designed a solution that required the use of two hydraulic lifting gantries.

450te lift and lock system was used to tranship the components from the transport onto a 6 axle SPMT. The pieces were then manoeuvred through gangways and stanchions to the second lift system, which was a 900te capacity system with side shift technology.

slash-brand-left-s
slash-brand-right

Precision planning and co-ordination

Both the moving plate and the fixed plate were then lifted into position on a pre levelled base. The team completed the tranship, transport and installation of the moving plate first and then repeated the process with the fixed plate.

Due to the size and description of vehicles in the delivery schedule and to maintain a smooth delivery, extensive planning and co-ordination was required with police, road closures and production departments to complete this project successfully.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.

slash-brand-left-s