slash-brand-left

Full service solution for four transformers

Allelys have provided the full service solution to offload, deliver and install four transformers, weighing 255te, at Dogger Bank Wind Farm.

The transformers were received in two shipments at Albert Dock in Hull, where the team lifted the vessels using Allelys’ LG1550 crane onto a 10 axle SPMT and shunted to a storage location for transhipment to our 350te girder frame trailer. They were then transported before the next shipment arrived.

Navigating a challenging route to site before installation

The transformers, measuring 9.5m long, 4.9m wide and 4.9m high, were loaded into a 350te girder frame and transported over four consecutive weekends to Creyke Beck Substation.

The transport arrangement, measuring 70m long and weighing 397te, had to navigate a challenging route, which included 3 structures that required bridge inspections and AIP’s to be submitted. The significant road works and road layout changes at Jock’s Lodge also posed a challenge, however the team identified and established a new route in advance of the project start date.

Once on-site, the units were also installed using a jacking and skidding system. The units were jacked up, the skid gear positioned underneath and then skidded into position in four separate bunds. Allelys used turntables to rotate three of the four transformers and a two directional skid for the final unit.

slash-brand-left-s
slash-brand-right

“We were involved at every stage of the project from completing letter drops, organising street furniture removal and temporary traffic management, through to project management and engineering support. To achieve four deliveries on consecutive weekends is a testament to the team’s hard work and ensured that the operation was completed on time.”

said Zac Smout, Senior Project Manager at Allelys.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.

slash-brand-left-s