slash-brand-left

Discover the equipment used and the services provided on this project by clicking the link below:

Delivery of ten 48m long bridge beams

Allelys have successfully delivered ten 48m long bridge beams as part of the M6 Junction 10 improvement scheme.

The project was split into two phases, with five beams delivered in July and five in September. The beams, ranging in weight from 92te to 122te, were required to be delivered in convoy during the pre-set road closure.

Due to the length of the beams, Allelys completed an in depth route survey to identify the best possible route and measure the pinch points along that route. Swept path analysis was also completed to ensure that the transport configuration could successfully pass through with the abnormal loads.

A solution was engineered to utilise specialist trailers in a 4 axle plus 6 axle configuration with bolstered turntables to enable manoeuvrability of the bridge beams along the designated route.

Each set of five bridge beams were transported 165 miles from Darlington to junction 10 of the M6.

In addition to the transportation services, the Allelys team also provided full engineering and project management support.

slash-brand-left-s
slash-brand-right

“With a road closure in place on the M6 to complete the scope of work, it was essential that Allelys met the delivery schedule. Each set of five bridge beams were required to be delivered in convoy and the team worked seamlessly together to successfully deliver the cargo.”

explained Zac Smout, Project Manager at Allelys.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.

slash-brand-left-s