Four transformers weighing 255te each

Allelys has successfully completed the 2nd of 3 packages of work for the Dogger Bank B onshore converter station, part of the world’s largest offshore wind farm.

This scope of work was to receive four transformers, each weighing 255te and measuring 9.3m long, 4.2m wide and 4.8m high at Albert Dock in the Port of Hull, before transporting them to site and installing them in their final positions.

Seamless solution across 4 consecutive weekends

Initial pre-works and engineering studies had suggested that Albert Dock would be unsuitable to accommodate the offload of the transformer units and that the project may be at risk of a significant setback. However, Allelys’ experienced in-house engineering team developed a bespoke crane mat and load spreading solution, to enable the lifting operations to proceed whilst adding vital protection to the quayside.

In order to successfully offload the vessel, Allelys rigged the LG1550 mobile crane to safely load the transformers onto a 12 axle SPMT, which transported the loads across the docks to a suitable transshipment area. The transformers were transshipped to Allelys’ Faktor 5.5 girder frame trailer, with 350te capacity, ready for transportation to site.

slash-brand-left-s
slash-brand-right

The girder frame transportation took place over 4 consecutive weekends. Moving one transformer at a time before going back to reload the next. This carefully planned operation provided a seamless solution for our client to receive the transformers in the more efficient time frame.

Once each transformer arrived at site, each unit was installed using a combined approach of turntables, jacking and skidding systems, allowing Allelys to successfully turn, move and install the transformers in their designated bay.

“This project was a great project to work on and the slick operation of delivering four transformers, to four different bays over four consecutive weekends shows just how experienced Allelys are at delivering power generation projects. We’re able to efficiently engineer and deliver solutions that meet the requirements of each individual project, whilst also minimising disruption for our clients.”

commented Jordan Heath, Project Manager at Allelys.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.