Two 239te transformers successfully delivered

Allelys have recently completed the successful delivery of two transformers from Buckie Harbour, Banffshire in Scotland to Moray West Onshore Converter Station. The units both weighed 239te and measured 12.3m long, 4m wide and 4.6m high.

Prior to the operation, extensive planning and engineering works were completed to overcome the harbour’s restrictive layout and limited space.

Detailed transport and installation solutions

Allelys also completed detailed route surveys along the route, with swept path analysis on the most restrictive areas also identifying necessary street furniture removal requirements, which would ensure the load was delivered safely and securely to site.

The transformers were offloaded from the vessel using an LG1750 lattice boom crane and loaded directly onto SPMTs. The first unit was then transshipped onto a 24 axle girder frame trailer and laid into load hangers to allow for a more suitable offload procedure due to the long load length. Under police escort and with road closures in place, the first transformer was transported to site. After the unit was stooled off, the girder frame was then dismantled and able to return to collect the second transformer. Simultaneously, the first transformer was jacked down and skidded 18m onto the designated plinth.

slash-brand-left-s
slash-brand-right

Efficient timing plans

The girder frame was rebuilt at the port and the second transformer was loaded, transported and installed using the same process and route as the first. Transporting the two units on consecutive weekends enabled Allelys to maintain an efficient timing schedule.

“This project has been a great example of Allelys finding an efficient and effective solution to support the power sector. The tight restrictions around the harbour are a challenge for loads such as these. However, our knowledge and experience of route planning and management ensured that we engineered a suitable solution.”

Commented Jordan Heath, Project Manager at Allelys.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.

slash-brand-left-s