Allelys have delivered a Yankee dryer pressure vessel, weighing 137te, to a paper mill in Barrow in Furness.

The dryer was shipped from Karlstad, Sweden and delivered to Buccleuch Dock, where it was lifted off the vessel using Allelys LG1550 crane and positioned onto flat top trailers.

27m long transportation arrangement

Measuring 5.62m in diameter and 9m in length, the Yankee dryer was prepared for onward transportation using 10 axle flat top trailers with a 16.6te axle loading.

The Yankee dryer, measuring up to 6.84m high was then transported 3 miles to the local paper mill in a transport configuration with a total length of 27m. Despite the short distance, the sheer size of the load meant that the route required street furniture to be removed and a police escort.

Once on-site, the transport arrangement was reversed into storage and the dryer was stooled off.

slash-brand-left-s
slash-brand-right

“For this operation our experts undertook the complete full service solution by providing project management and engineering support, including a route surveyswept path analysislift plan and lift management. To navigate such a long transportation arrangement on A-roads is no mean feat and I’m proud that the team delivered this safely and on schedule.”

said Zac Smout, Senior Project Manager at Allelys.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.