Frodsham substation reactor

Allelys have successfully completed the transport and installation of a 113te reactor for Frodsham substation.

The reactor, measuring 6.5m (l) x 2.7m (w) x 4m (h) was received at Immingham port and transported to Frodsham using 12 axle lines of modular trailers.

Use of a temporary bridge to access the installation site

Once on site, the unit needed to be transported across a waterway and required the use of a temporary bridge. Allelys jacked up the bridge, positioned rollers underneath and connected winches. The bridge was then winched across the waterway on the rollers.

100te capacity mobile crane then lifted the nose off the bridge to allow it to be lowered down into position on the embankment, where it sat on feet that had been positioned and installed by the Allelys team.

The truck carrying the unit was configured with an extendable drawbar. The drawbar was extended to its maximum length of 10m and the truck was reversed up to the bridge until the back wheels of the truck met the bridge, positioning the reactor as far across the bridge as possible. The truck was then disconnected from the trailer. The second truck waiting on the far side of the bridge then connected winches to the trailer to winch the unit across the remaining distance of bridge and back onto land.

The final stage within Allelys scope of work was to install the reactor into its final position using a jacking and skidding system.

slash-brand-left-s
slash-brand-right

“Being a temporary bridge, the weight capacity wouldn’t allow both the truck and trailer on the bridge at the same time. Therefore we devised a solution to position a truck on each side of the bridge, to transport the reactor as far as we could and then winch it the remaining distance.”

explains Craig Mackay, Operations Manager – Projects at Allelys.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.

slash-brand-left-s