Heavy lift offload using the LG1550

Allelys have successfully installed two components, a turbine and a generator, through the roof of a turbine hall at a height of 22.3m.

The turbine, weighing 160te and measuring 7.8m (l) x 5.35m (w) x 4.6m (h) arrived into Goole docks, where Allelys discharged the vessel using the LG1550 mobile crane. It was then positioned onto stools at the port for temporary storage.

Diligent transport planning and delivery

Once the site team were ready to receive the component, Allelys built a 24 axle girder frame trailer around the stools to self-load the cargo, ready for transport to Skelton Grange.

“Prior to the transport phase, Allelys completed route surveys and transport arrangement designs as well as swept path analysis for the journey through site. Our engineering reports identified two structures that required to be negotiated on site, Wyke Beck Bridge and Effluent Culvert,” explained Garnaud Tsika, Commercial Manager at Allelys.

slash-brand-left-s
slash-brand-right

Utilising combined techniques

“Assessments were completed on both of these structures prior to project award. The assessments detailed that using a 16 axle girder frame, typical for the size and weight of this unit, wasn’t suitable, therefore we designed a solution to use a bigger and lighter frame to overcome these challenges, which enabled the route to be cleared.”

The transportation stage included a night time closure on the A1 to open up the carriageway central reservation and allow the transport to cross over and join the M1.

Final positioning using the LG1550

Once at site the turbine was transshipped from the girder frame onto a 12 axle SPMT, due to the restricted space available. It was transported to within the radius of our LG1550 crane and lifted into the turbine hall.

Allelys also received the second component at site, a 96te generator, where it was temporarily stooled off and then transported using the same 12 axle SPMT, to the crane location for lifting.

“The turbine hall was still in construction and there was a number of restrictions that we needed to adhere to, including the precise planning that was required to modify the crane location and position the outriggers due to non load bearing areas.”

With the height of the building being 22.3m, the LG1550 was rigged in luffing jib configuration. The turbine was lifted and installed first, followed by the generator, with both being lifted directly onto their final positions with the meticulous precision required to negotiate the limited clearance.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.