slash-brand-left

Tummel transformer deliveries

The initial phase of work began two years prior to the delivery of the transformers, with Allelys supporting the planning phase by completing a route study to identify a suitable route to a difficult location. The work involved swept path analysis, over 30 structural bridge assessments, tree trimming and numerous site visits.

Allelys identified that the nearest suitable port was Dundee. The transport then needed to navigate Friarton bridge on the A90 at Perth, head north on the A9 to Ballinaluig, continue via the A827 towards Aberfeldy and through Strathtay village to keep north of the River Tay as it could not be crossed in Aberfeldy.

A complex route

The first part of the route, from Dundee to Ballinaluig, was completed on a Saturday afternoon and the second part of the route, to site, was completed the following day with two transformers in convoy. This was to limit the disruption caused within peak times and to the school bus services. Sections of the route were very narrow, with some challenging turns and bridges. The final stage of the route also took the loads up to the snow line and then back down to the valley floor. It took a total of 10 hours to complete the distance of 23 miles due to the challenging route.

slash-brand-left-s
slash-brand-right

Route preparations

A number of route preparations were required prior to the transport, including over bridging two structures, widening the road in a number of places, tree trimming and rock clearance to move the road into the hillside to avoid the load damaging retaining walls on the climb up the hillside.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.

slash-brand-left-s