slash-brand-left

Transportation of 3 super grid transformers and 2 shunt reactors

Allelys were contracted to transport three 272te super grid transformers and two 77te shunt reactors from Peterhead Port, Aberdeenshire to Moray East Substation, New Deer, Aberdeenshire.

All of the units were shipped to Peterhead Port where Allelys used a Liebherr LG1550 heavy lift crane to offload the units from the delivery vessels to the port side storage.

Our 350te capacity ‘Faktor 5.5’ girder frame was utilised, with 10 modular axles at each end of the frame, to transport the super grid transformers. The unique design allowed the team to self-load the trailer without any outside assistance for each movement. The combined delivery weight, including the two MAN prime movers, was 484te and had an overall length of 66.7m.

The route

The transportation from Peterhead Port to Moray East Substation used the A90 before turning off onto smaller ‘A’ and ‘B’ roads. Numerous structures on the route had to be checked and cleared for load bearing capacity, resulting in special manoeuvres and speed restrictions being put in place. Travelling through small Scottish villages and hamlets with such a large vehicle also drew a lot of attention from the public.

slash-brand-left-s
slash-brand-right

Each super grid transformer was offloaded to its final position at the Moray East Substation, using our own hydraulic skid system and synchronised jacking equipment.

The two shunt reactors were delivered to site on flat top modular trailers from Peterhead Port and were offloaded to their final position using a Liebherr LTM1500 mobile crane.

In addition to the transportation and installation, Allelys also provided a fully engineered and project managed solution.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.

slash-brand-left-s