slash-brand-left

Discover the equipment used and the services provided on this project by clicking the link below:

Two Class 158 units

Allelys completed the removal and replacement of two 40te Class 158 diesel multiple unit (DMU) trains in Barmouth. The units located at this seaside town would usually be transported by rail, but due to a bridge being closed at Machynlleth, Allelys supported the project by transporting them by road.

The first stage of the project involved a detailed route study to identify a suitable route for the cargo, photographing challenging aspects of the route and measuring pinch points. This was followed by swept path analysis of specific junctions and crossroads along the route to simulate the heavy lift equipment and confirm that the route was possible.

Due to the size of the transport required, the route for this particular project was a total of 240 miles, beginning in Barmouth and moving through Llanuwchllyn, Corwen, Oswestry, Shrewsbury, Telford, Wolverhampton, Gloucester and Newport before being delivered in Cardiff two days later. The replacement units then completed the same 240 mile, 2 day route back to Barmouth.

slash-brand-left-s
slash-brand-right

The Class 158 units were transported using six axle rail trailers and two tractor units. The vehicles measured 30.8m (l) x 3m (w) x 4.85m (h) gross and weighed 90te. These rail trailers are purpose built for Allelys and the specialist rail projects we undertake. They enable our team to use a ramp and winch method to load the rolling stock, so the cargo doesn’t need to be lifted.

The transport route out of Barmouth, with the removed units, allowed the vehicles to travel in the correct direction of the one way system. However, when the replacement units were transported, Allelys co-ordinated with the Police to temporarily close the high street to enable the vehicles to travel against the one way system.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.

slash-brand-left-s