slash-brand-left

Successfully delivered a turnkey solution

Allelys complete 6.60m high strand jack gantry lift at Lostock Sustainable Energy Plant.

Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant. The project scope included the transportation, lifting and installation of a 154te steam turbine and a 132te generator from Ellesmere Port to the plant in Northwich.

Designing an appropriate solution

The transport would have been possible on a shorter configuration, however due to weight restrictions on the approach to site, Allelys utilised an 18 axle modular trailer to deliver both the steam turbine and generator to site on a consecutive movement. Upon arrival, both the turbine and generator were stooled off and temporarily stored until required for installation.

slash-brand-left-s
slash-brand-right

Combining techniques

The generator was then self-loaded onto a 10 axle SPMT for transport across to the installation area, whilst traversing over a condenser pit which Allelys overbridged. It was positioned under the hydraulic strand jack gantry system and lifted to a 6.60m high plinth. The generator was then skidded approximately 20m to its final position.

The same operational process was used to tranship the turbine onto the SPMT, position it under the hydraulic gantry system, lift, skid and install to final position.

Demonstration of engineering capabilities

“This project was a clear demonstration of the engineering capabilities within the Allelys business. Our engineering team developed a bespoke strand jack system design concept, and overbridging design, to ensure the successful delivery and installation of these critical components,” Explained Garnaud Tsika, Commercial Manager at Allelys.

Showcasing agility and flexibility

“We also showcased our agility and flexibility when faced with unexpected ground loading constraints on site. The site ground loadings were lower than what we were going to impose, however we re-engineered the project and by using additional equipment, we were able to adapt and meet the site conditions.”

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.
Allelys played a pivotal role in the Grand Surrey Canal project with the site transport and installation of 15 precast concrete arch sections.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.