Railcar delivery to the Global Centre of Rail Excellence

Allelys recently completed the lifting and transportation of a Talgo railcar measuring 13.7m (l) x 2.94m (w) x 3.62m (h) and weighing 20te. The railcar was transported from Barrow Hill Railway Roundhouse in Chesterfield to the Global Centre of Rail Excellence in Onllwyn.

Our in-house engineering team identified a suitable route and engineered a transport arrangement on Allelys bespoke 5 axle Goldhofer rail trailer.

Complex lifting and transportation solutions

“The first stage of the operation was to load and secure the railcar onto the trailer. Typically we would use a ramp and winch technique, however due to the complex design and construction of this particular railcar, a solution was designed to complete a tandem crane lift to safely load the cargo,” explained Jamie Woodland, Commercial Manager at Allelys.

Allelys managed all of the lift requirements internally, including designing the appropriate lifting solution, creating detailed lift plans and providing specific method statements and risk assessments. The team then utilised our 100te and 200te mobile cranes, along with appropriate lifting tackle, to safely and securely load the railcar to the trailer.

slash-brand-left-s
slash-brand-right

Once the railcar was successfully loaded to the 5 axle rail trailer and tractor unit combination, it was then able to begin its transportation to site. Travelling across a long and challenging route, overcoming tight corners and difficult pinch points along the way, the load arrived at the Global Centre of Rail Excellence site in Onllwyn, South Wales, where the cargo was safely offloaded and delivered via a second tandem crane lift operation.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.

slash-brand-left-s