Transportation from Ipswich to Burwell

Allelys have recently transported, offloaded and installed a transformer weighing 184te. The cargo was received at Ipswich Docks onto a 12 axle flat top trailer and shunted to a temporary storage area.

The transformer, measuring 8.7m (l) x 5.4m (w) x 4.8m (h), was then transported 59 miles to Burwell, Cambridge using an 18 axle, 200te capacity girder frame. The route engineered by the Allelys team, included a temporary closure of the Orwell Bridge to enable the transport to cross without any other vehicles on the bridge at the same time.

A complex project route

Working alongside Highways England, Allelys arranged temporary traffic management on the A14 to remove the central reservation barrier and with two lanes closed on each side, the girder frame was able to cross over, travel against the normal flow of traffic and up the slip road, at junction 37, on the wrong side of the carriage way.

The heavy transport then needed to negotiate the intricate road network through the town of Burwell, before delivery to the substation.

Once on site, the transformer was jacked up using synchronised climbing jacks and positioned onto a turntable to be rotated, skidded into the bund and then jacked down into its final position.

slash-brand-left-s
slash-brand-right

A full service solution

The in-house engineering team supported the project to ensure that the abnormal load was able to successfully travel through the selected route by completing route surveys and swept path analysis. They also engineered a lift plan for the crane work on site.

“This project was particularly interesting to work on due to the route involved. It was certainly impressive to see the girder frame travelling solo across the Orwell Bridge. The knowledge and experience within the team, alongside the Allelys equipment fleet, were all critical elements to the success of the project.”

explained Zac Smout, Project Manager at Allelys.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.

slash-brand-left-s