Allelys provide transport solution for Slough Multifuel Expansion project

Power

Equipment Used:

  • Mobile crane
  • Mats
  • Stools
  • Low loader
  • Modular trailer
  • Step frame
  • Super low step frame
  • Vessel deck
  • Tractor unit
  • Standard flat trailer
  • Extendable flat trailer
  • Van
  • Wafer bed
  • Forklift

Share:

Services Provided:

  • Transportation
  • Route study
  • Lift study
  • Lift plan
  • Lift management
  • Project management
  • Engineering
  • Consultation
  • Load spreading
  • Lifting
  • Swept path analysis
  • Warehousing
Allelys general haulage vehicles on the road transporting a green unit

Delivering multiple scopes of work

Allelys played a pivotal role in the Slough Multifuel Expansion project and were awarded with seven separate scopes of work.

Two of the scopes of work were awarded by the same client and required Allelys to receive and deliver 10 pieces from Felixstowe to Slough and 5 pieces from Tilbury to Slough, whilst taking full responsibility for project management. The pieces, ranging in weights from just under 1te to 39.5te, included components such as a gate drive unit, feed hopper and filter chambers.

Extensive planning and complex time constraints

The first components arrived into Felixstowe on two individual vessels, with 5 pieces of project cargo on each. The geared vessel lifted the units onto Allelys trailers ready to be transported.

The cargo was transported from Felixstowe to Reading Services’ abnormal load bay and then continued to site in Slough. The components were transported in two separate moves per day, on two consecutive days.

The second components, including a pressure water tank, two semidry reactors and two raw gas ducks, arrived into Tilbury and were transported to site using vessel bridge and wafer deck trailers.

“This project included tight time constraints that needed to be overcome within the planning phase. The site required the delivery of the loads within dedicated time slots early in the day, however local embargoes meant that we couldn’t move through the local area before 10am. Therefore, a plan was devised to drive to Reading and then hold the cargo in the abnormal load bay until the time embargoes had passed. Then the final leg of the journey could be completed in time to arrive in the allocated time slot.” Explained Simon Davies, Project Manager at Allelys.

Together these projects demonstrate Allelys ability to devise bespoke transport configurations to deliver a diverse volume of cargo.

Let's talk about what Allelys can do for your business

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.



We've been quite busy lately!

Strand jack lifts at Lostock

Allelys deliver turnkey solution at Lostock Sustainable Energy Plant.

Three abnormal loads for Hirwaun

Allelys transport and installation three abnormal loads for Hirwaun Power Station.

Allelys install 15 arch sections

Allelys played a pivotal role in supporting the Grand Surrey Canal project.

Certified marks Certified members mark Certified marks