slash-brand-left

Two 317te turbines and two record breaking 370te generators

Allelys have successfully completed the transport of four units from Belfast Harbour to Kilroot Power Station in Northern Ireland. The four units comprised of two turbines weighing 317te each and two generators weighing 370te each, with the generators breaking the existing record for the heaviest loads to be transported on Northern Ireland’s road network.

The generators arrived into Belfast from the USA, whilst the turbines arrived from Europe. All four were offloaded via geared vessel onto Allelys trailers positioned in the harbour, transported to a temporary storage area and stooled off.

Transport to Kilroot power station

In preparation for transport, one turbine and one generator were then brought out of storage using SPMT’s and the girder frames built around the units. The Faktor 5 in 28 axle configuration for the generator and the Faktor 5.5 in 28 axle configuration for the turbine. The two units were then transported in convoy during a night move to Kilroot Power Station.

“This project demonstrates Allelys expertise in heavy lift and specialist transport,” commented Richard Beardmore, Senior Commercial Manager at Allelys. “The business has continued to invest in the latest equipment to be able to offer a full-service solution to the industry, leading projects such as this.”

Once at site, the generator was transhipped back onto SPMT, transported to the turbine hall, lifted with a four-point lift system, lowered onto foundation. The same process was then repeated with the turbine.

slash-brand-left-s
slash-brand-right

A full service solution

The team then travelled back to Belfast to load the remaining two units and repeat the transportation and installation phases.

“Not only was this the second double girder frame convoy of the year, it was also a record breaking project due to the weight of the cargo. It was great to see the interest from the public and local media that came out to witness the move throughout the night.” concluded Richard Beardmore.

Allelys provided a full-service solution for this project including engineeringroute surveys, structural assessments of 20 structures, project management, transportation and installation.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.

slash-brand-left-s