Allelys completes multi project Shetland transformer deliveries

Power

Equipment Used:

  • Mobile crane
  • Franna crane
  • Climbing jack
  • Mats
  • Stools
  • Low loader
  • Modular trailer
  • SPMT
  • Step frame
  • Neck
  • Tractor unit
  • Standard flat trailer
  • Van
  • Telehandler
  • Ramp trailer

Share:

Services Provided:

  • Transportation
  • Installation
  • Route study
  • Lift study
  • Lift plan
  • Lift management
  • Structure analysis
  • Ground analysis
  • Bridge analysis
  • Project management
  • Engineering
  • Consultation
  • Palletised goods
  • Fabrication
  • Load spreading
  • Overbridging
  • Skidding
  • Jacking
  • Lifting
  • Roll-on / Roll-off
  • Swept path analysis
  • External storage
  • Internal storage

Allelys provide a full service solution

As part of a full turnkey solution, Allelys delivered and installed eight transformers across two separate projects for the Kergord Energy Substation and Viking Energy Substation on the Shetland Islands.

The first project involved transporting four transformers, all weighing 168te and measuring 7.5m long, 4m wide and 4.5m high, using a 15 axle modular trailer from Lerwick Port to the Kergord Substation.

Consistently delivering on multi stage projects

The units arrived in pairs into the port and were offloaded by a geared vessel. As one was temporarily stored, another was transported to the site. The cargo, which measured 35m long, 4m wide and 5.5m high, had to traverse multiple steep hills into the site, requiring two tractor units to pull the units up the first hill. They were then transhipped to an 18 axle SPMT, manoeuvred up the second hill and down the final steep hill into site. The transport route was then repeated for the unit left in storage, before the second pair arrived into the port and the whole operation repeated.

Once on site, they were installed using jacking and skidding techniques in multiple stages. Firstly, transformers one and two were stooled in front of plinth and rotated 90 degrees, they were then jacked and skidded into position. The operation was then replicated for transformers three and four.

For the second project, the four transformers, all weighing 94te, arrived via barge into Rotterdam, where they were transhipped via mobile crane onto Allelys 2 bed 4 trailers and ferried over in pairs to Immingham.

Providing multi-modal project solutions

The Allelys team were tasked with the 400 mile road transportation to Aberdeen, arranging the sea transportation to Lerwick Port, and onwards road transportation to Viking Energy Substation with a total transport length of 28m and height of 4.8m. Once on site, the transformers were then offloaded externally to be assembled and built, before being jacked and skidded onto the plinth.

“With multiple units arriving from different countries in such a remote part of the UK, this was not an easy task. These multi-phase and multi-modal projects really showcased our range of equipment and techniques, incorporating the team’s dedicated project management and engineering services over several months,” said Zac Smout, Senior Project Manager at Allelys.

Let's talk about what Allelys can do for your business

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.



We've been quite busy lately!

Complex delivery to Rothienorman

352te generator and 158te transformer delivered to Rothienorman Substation.

Slough Multifuel Expansion project

Providing transport solutions across several scopes of work.

First delivery to Eye complete

First delivery, of a 327.5te generator delivered to Progress Power Station.

Certified marks Certified members mark Certified marks