slash-brand-left

Allelys provide a full service solution

As part of a full turnkey solution, Allelys delivered and installed eight transformers across two separate projects for the Kergord Energy Substation and Viking Energy Substation on the Shetland Islands.

The first project involved transporting four transformers, all weighing 168te and measuring 7.5m long, 4m wide and 4.5m high, using a 15 axle modular trailer from Lerwick Port to the Kergord Substation.

Consistently delivering on multi stage projects

The units arrived in pairs into the port and were offloaded by a geared vessel. As one was temporarily stored, another was transported to the site. The cargo, which measured 35m long, 4m wide and 5.5m high, had to traverse multiple steep hills into the site, requiring two tractor units to pull the units up the first hill. They were then transhipped to an 18 axle SPMT, manoeuvred up the second hill and down the final steep hill into site. The transport route was then repeated for the unit left in storage, before the second pair arrived into the port and the whole operation repeated.

Once on site, they were installed using jacking and skidding techniques in multiple stages. Firstly, transformers one and two were stooled in front of plinth and rotated 90 degrees, they were then jacked and skidded into position. The operation was then replicated for transformers three and four.

For the second project, the four transformers, all weighing 94te, arrived via barge into Rotterdam, where they were transhipped via mobile crane onto Allelys 2 bed 4 trailers and ferried over in pairs to Immingham.

slash-brand-left-s
slash-brand-right

Providing multi-modal project solutions

The Allelys team were tasked with the 400 mile road transportation to Aberdeen, arranging the sea transportation to Lerwick Port, and onwards road transportation to Viking Energy Substation with a total transport length of 28m and height of 4.8m. Once on site, the transformers were then offloaded externally to be assembled and built, before being jacked and skidded onto the plinth.

“With multiple units arriving from different countries in such a remote part of the UK, this was not an easy task. These multi-phase and multi-modal projects really showcased our range of equipment and techniques, incorporating the team’s dedicated project management and engineering services over several months.”

said Zac Smout, Senior Project Manager at Allelys.

More Case Studies

Each and every project is unique. Our vast service offering and extensive equipment fleet enables us to work on some of the most exciting and challenging projects within the UK. Take a look at a selection of our case studies below.

Allelys have successfully completed the transport and crane lift operation for the installation of a 146te Yankee drying cylinder at Shotton Mill in Flintshire.
Allelys’ AK912 mobile crane returned to the UK market to lift critical infrastructure at Port of Sutton Bridge. This project marked the AK912’s first project lifts since the crane underwent a full refurbishment.
Allelys has successfully delivered a turnkey solution for the transport and installation of critical equipment at the Lostock Sustainable Energy Plant.
Allelys have successfully completed the transport and installation of a 309.5te turbine, 326.1te generator and 221.8te transformer from Newport Docks to Hirwaun Power Station.

Lets Talk...

We would love to hear more about the challenges you are facing. This form below will help us understand that project better and one of our experienced members of the team will be pleased to help you.

slash-brand-left-s